compute + power infrastructure.
Local LLM infrastructure calculator
Find the useful delta between watts, tokens, and dollars.
Model a local 70B-class host, choose how it is powered, and compare the trade-off between immediate compute value, lifecycle cost, and energy independence.
Infrastructure model
Balance compute, power, and capital.
Compare documented local LLM hardware profiles across grid, hybrid grid-tied solar, and dedicated off-grid solar. The model prioritises 70B-class inference and reports both upfront and lifecycle TPS per dollar.
Selected configuration
/
Higher means more projected 70B throughput per upfront dollar.
modeled grid energy over the selected lifecycle.
Lifecycle score including grid energy, but excluding maintenance and replacement.
Estimated watt-hours required to generate 1,000 tokens at sustained output.
Power build
Requirements based on the selected hardware.
At , before demand charges or tariff escalation.
Power strategy comparison
Same hardware, different power architecture.
| Power strategy | Power CapEx | Overall CapEx | Annual grid OpEx | 3-year TCO | TPS / TCO × 10k |
|---|---|---|---|---|---|
| Standard grid | |||||
| Hybrid grid-tied | |||||
| Off-grid solar |
Fit, pros, and risks
What this selection optimises, and what it gives up.
Documented equal-budget benchmark
Reinvesting power infrastructure into compute changes the winner.
These presets reproduce the three strategy examples in calculationInformation.md.
Load one to continue adjusting its assumptions above.
- Pool
- 2x RTX 3090
- Upfront
- $25,750
- 3-year TCO
- $25,750
- TPS / TCO × 10k
- 5.82
- Pool
- 6x 3090 / 4 active
- Upfront
- $24,500
- 3-year TCO
- $26,768
- TPS / TCO × 10k
- 13.07
- Pool
- 6x RTX 3090 farm
- Upfront
- $19,000
- 3-year TCO
- $22,801
- TPS / TCO × 10k
- 18.42
Planning model only. Hardware speeds, component costs, solar yield, and battery autonomy are
estimates transcribed from calculationInformation.md, not supplier quotes or
guaranteed benchmarks. Validate the final electrical design with a qualified installer and
benchmark the intended model, quantisation, context length, and serving stack before purchase.
Generator backup, maintenance, finance cost, hardware replacement, cooling installation, demand
charges, and tariff escalation are not included.